Production relocation, Large-format digital printing, Germany

Production relocation without supply interruption

A relocation succeeds when it is planned long before the first machine is taken down. During the move, a specialist service team inspected and serviced the equipment, and production restarted on time at the new site.

Client
Large-format digital printing company
Industry
Large-format digital printing
Location
Germany
Duration
24 months
Services
Production relocation, Ramp-up management

Project brief

Starting point
Move of the printing and finishing production to a site 150 km away with two halls of 3,000 m² each
Methods
Strategic relocation planning months in advance, technical inspection and servicing during dismantling and set-up
Stakeholders
Executive management, specialist service team, workforce
Result
Major US contract; plant 2 ramped up with partial digitalisation; scrap 10 → <1.5 %; 5S/CI; high single-digit EBIT; local handover in 24 months

Measurable. Traceable.

15machines
printing and finishing machines relocated
150km
distance to the new site
24months
until handover to local management

2 × 3,000 m² hall space at the new site. The ramp-up was on time – with an optimal flow of goods and a highly motivated team.

From the starting point to the result.

Challenge

The entire printing and finishing production had to move to a site 150 kilometres away: 15 machines spread across two halls of 3,000 m² each. Production then had to restart on time.

  • 15 printing and finishing machines
  • 150 km to the new site
  • Two halls of 3,000 m² each

Approach

WOLF planned the move strategically months in advance. While the machines were being dismantled and set up again, a specialist service team inspected and serviced them, so they went into operation at the new site in good condition.

  • Relocation planning months in advance
  • Technical inspection and servicing during the move
  • Flow of goods for the new site

Result

Major US contract secured. Second plant ramped up with a partially digitalised value stream and production flow. Scrap reduced from 10 % to below 1.5 %. 5S and continuous improvement introduced. High single-digit EBIT achieved. Handover to the local management team within 24 months.

  • Major US contract secured
  • Second plant ramped up with a partially digitalised value stream and production flow
  • Scrap reduced from 10 % to below 1.5 %
  • 5S and continuous improvement introduced
  • High single-digit EBIT achieved
  • Handover to the local management team within 24 months

The path to the result.

24 months

  1. Months before

    Strategic planning

    Relocation roadmap and flow of goods for the new site.

  2. Month 1–2

    Dismantling & set-up

    Move of the 15 machines with parallel inspection and servicing.

  3. Month 2

    Ramp-up

    On-time start of production at the new site.

What WOLF was responsible for in this project.

Production relocation

Relocation planning in waves, safety stocks and requalification without supply interruption.

Learn more

Ramp-up management

KPI-driven ramp-up, quality assurance and stabilisation up to target capacity.

Learn more

A similar starting point?

Let's talk about your plans – no obligation, at eye level.