Start-up & plant construction, Textiles / high-tech manufacturing, Eastern Europe

From brownfield to series in 18 months

There are countries where a large brownfield start-up is as hard as pitching a tent in 100 km/h gusts. Everything is feasible – but only with cultural understanding, international experience and a team resilient to setbacks.

Client
Textile producer
Industry
Textiles / high-tech manufacturing
Location
Eastern Europe
Duration
2 years
Services
Plant construction, Ramp-up management, Interim management

Project brief

Starting point
Brownfield start-up with 250 employees and international management
Methods
Change and lean management, project management, leadership, 5S
Stakeholders
Owner, management and 250 employees
Result
USD 100m brownfield; 6-month skilled-worker training for 250 FTEs; USD 40m machinery; SOP 18 months; defects <2.5 %; training/local handover 24 months

Measurable. Traceable.

18months
from brownfield to launch
250employees
built up and qualified
<2.5%
defect rate in high-tech manufacturing

Expat team as engine. An experienced expat team got the project off the ground against the wind – with a local project manager as a must, not a nice-to-have.

From the starting point to the result.

Challenge

Lean was almost a foreign word in the local working and bureaucratic culture. High-tech production with strict defect tolerance needs several attempts before quality is sustainably right – at above-average cost in time and money.

  • Brownfield without an existing organisation
  • 250 employees to be built up from scratch
  • Cultural resistance to lean and efficiency

Approach

An expat team with many years of international experience acted as an additional engine. Agile project management gave the teams daily orientation; change and lean management and 5S created standards. Goal: as good as necessary – not as good as possible.

  • Agile project management as the gold standard
  • Professional local project manager
  • Leadership and change management for the majority of the team

Result

Brownfield start-up with a project value of USD 100 million. Recruitment and six-month training of 250 FTEs to qualify as skilled workers. Installation and commissioning of machinery worth USD 40 million. Launch / SOP after 18 months. Defect rate below 2.5 %. Training and handover to the local management team after 24 months.

  • Brownfield start-up with a project value of USD 100 million
  • Recruitment and six-month training of 250 FTEs to qualify as skilled workers
  • Installation and commissioning of machinery worth USD 40 million
  • Launch / SOP after 18 months
  • Defect rate below 2.5 %
  • Training and handover to the local management team after 24 months

The path to the result.

2 years

  1. Month 0–4

    Concept & team

    Project plan, expat team and local project manager.

  2. Month 4–12

    Build-up & recruiting

    Plant, organisation and 250 employees built up.

  3. Month 12–18

    Start-up & launch

    Several quality runs up to launch.

  4. Month 18–24

    Stabilisation

    Defect rate reduced, handover to local management.

What WOLF was responsible for in this project.

Plant construction

Site analysis, business case, plant layout and management of construction and installation.

Learn more

Ramp-up management

KPI-driven ramp-up, quality assurance and stabilisation up to target capacity.

Learn more

Interim management

Plant and general management on a temporary basis – until handover to the local leadership team.