Lean & cost, Medical devices, Switzerland

Quality and delivery dates under control

Cost, time and quality are antagonists – but only once all three are already optimised. Here, quality problems arose from time pressure, and time pressure from missing production planning. WOLF broke the vicious circle.

Client
Medical device manufacturer
Industry
Medical devices
Location
Switzerland
Duration
12 months
Services
Interim management, Ramp-up management

Project brief

Starting point
Quality problems, excessive production costs, capacity bottlenecks
Methods
Strategic management, KAIZEN, 5S, value stream analysis
Stakeholders
Owner, management and all employees
Result
Scrap ≤ 1 %, 95 % on-time delivery, 7 % cost reduction

Measurable. Traceable.

≤1%
scrap rate
95%
deliveries on time
7%
reduction in production costs

R&R restored. Repeatability and reproducibility of the processes back at a high level – in machine technology as well as chemical formulation.

From the starting point to the result.

Challenge

Recurring quality problems cost orders, the lack of profitability prevented investment, and without production planning the team was under constant time pressure. Sales won orders – and lost them again.

  • Quality problems with regulated medical devices
  • No PPS, no reliable production planning
  • Capacity bottlenecks and cost pressure

Approach

Ask “why” six times: the chain of causes led from scrap via time pressure to the missing operations management. A professionally run PPS, KAIZEN, 5S and value stream analyses created time and capacity.

  • Root cause analysis based on lean six sigma
  • Introduction of a managed PPS
  • Resolution of technical and chemical formulation problems

Result

Scrap reduced to a maximum of 1 %, 95 % of delivery dates met, production costs cut by 7 %. Sales no longer lost orders – revenue grew and new capital for investment was created.

  • Scrap ≤ 1 %
  • 95 % on-time delivery
  • 7 % cost reduction

The path to the result.

12 months

  1. Month 0–2

    Root cause analysis

    Cause-and-effect chain from scrap to organisation.

  2. Month 2–5

    PPS & planning

    Production planning and control introduced and managed.

  3. Month 5–10

    KAIZEN & 5S

    Value stream analyses and improvements in all areas.

  4. Month 10–12

    Stabilisation

    Quality and delivery KPIs sustainably anchored.

“The technical problems with chemical formulations as well as machine-related issues were solved. Repeatability and reproducibility are back at a high level.”
Head of Quality & Compliance Management, Medical device manufacturer, Switzerland

What WOLF was responsible for in this project.

Interim management

Plant and general management on a temporary basis – until handover to the local leadership team.

Learn more

Ramp-up management

KPI-driven ramp-up, quality assurance and stabilisation up to target capacity.

Learn more

A similar starting point?

Let's talk about your plans – no obligation, at eye level.